A 200 member project team is working on a large and complex system with multiple sub-systems. They would like to start using the Agile Scrum methodology.

As a Scrum Master, what would your best advice be?


A.

Scrum is not suited for such a large project. The team should clearly use the Waterfall method or the Crystal Clear method.


B.

Ask all potential members of the project team to have a meeting first and decide if they agree to use Scrum.


C.

Agree a logical sub-division of the system so that smaller Scrum teams can work on sub-systems and can add tangible value.