Exin Agile Scrum Foundation EX0-008 Question # 2 Topic 1 Discussion

Exin Agile Scrum Foundation EX0-008 Question # 2 Topic 1 Discussion

EX0-008 Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three points.

Which statement is true regarding this scenario?


A.

Points are assigned by the Scrum Master, not by the team.


B.

Points are assigned for the overall Story, not for parts of the Story.


C.

Points are never estimated, but always determined beforehand.


D.

The team forgets to ask the Product Owner about the estimate.


Get Premium EX0-008 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.