New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exin EXIN EPI Certified Information Technology Manager CITM Question # 15 Topic 2 Discussion

Exin EXIN EPI Certified Information Technology Manager CITM Question # 15 Topic 2 Discussion

CITM Exam Topic 2 Question 15 Discussion:
Question #: 15
Topic #: 2

Before signing the contract with the proposed vendor, concerns have been raised over future price increases. The internal business units, however, insist that the agreement with the vendor must take place as a result of the vendor evaluation process. What is the likely action to take?


A.

Ignore the business units and change vendor


B.

Include contractual terms


C.

Sign the contract


D.

Re-tender the project


Get Premium CITM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.