Question #: 15
Topic #: 2

Before signing the contract with the proposed vendor, concerns have been raised over future price increases. The internal business units, however, insist that the agreement with the vendor must take place as a result of the vendor evaluation process. What is the likely action to take?


A.

Ignore the business units and change vendor


B.

Include contractual terms


C.

Sign the contract


D.

Re-tender the project