Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exin EXIN EPI Certified Data Centre Specialist CDCS Question # 19 Topic 2 Discussion

Exin EXIN EPI Certified Data Centre Specialist CDCS Question # 19 Topic 2 Discussion

CDCS Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

Management has requested a 15-minute battery bank assuming full load on the UPS. The UPS vendor has provided the following specifications of the UPS:

•Rated power: 30 kVA

•Rectifier input voltage: 400 V/3 phase

•Rectifier input power factor: 0.8

•Battery rated voltage: 384 V

•Number of cells: 192

•End of discharge voltage: 308 V

•Inverter output voltage: 400 V/3 phase

•Inverter output power factor: 0.8

What information is missing to perform the battery calculation?


A.

UPS efficiency


B.

Inverter efficiency


C.

Load imbalance on the phases


D.

Available battery charging current


Get Premium CDCS Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.