A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lbs is going to be installed in the data center.

Are new floor loading calculations required?


A.

No, as long as the equipment is less than 700 kg/1,500 lbs it will be within the limits.


B.

No, specifications of equipment brought into the data center will already be known during the design of the data center, and therefore the floor will be able to handle it.


C.

Yes, additional floor loading calculations need to be done by the floor manager, which should be verified by the safety engineer.


D.

Yes, a structural engineer, approved/endorsed by the building owner, should carry out new floor loading calculations.