A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis.

What is the elapsed time required to complete the story?


A.

1.25 days


B.

1.33 days


C.

2 days


D.

This cannot be determined without knowing the velocity.