EMC Dell PowerEdge XE9680 and XE8640 Install D-PEXE-IN-A-00 Question # 1 Topic 1 Discussion

EMC Dell PowerEdge XE9680 and XE8640 Install D-PEXE-IN-A-00 Question # 1 Topic 1 Discussion

D-PEXE-IN-A-00 Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

A deployment engineer is installing a PowerEdge XE8640 server. The server is on a lift, and they have aligned the server inner rails with the rail assemble that are secured in the rack. The engineer

can only push the server into the rack a short distance before it stops. Pushing forcefully causes the rack to slide back.

What action should the deployment engineer take?


A.

Press the mechanism on the rail to release the rail lock.


B.

Lower the lift and move away from the server.


C.

Pull the server out of the rack and realign the lift with the rack.


D.

Have a person hold the rack while using force to slide in the server.