Question #: 18
Topic #: 2

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?


A.

A project manager assigned the wrong resources.


B.

A project manager did not release the resources


C.

A project manager did not remove the system access.


D.

A project manager did not provide the project sign-off.