Question #: 18
Topic #: 2

A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?


A.

Identify project risks and plans to address them.


B.

Identify business needs and product descriptions.


C.

Create a work breakdown structure for the project.


D.

Create a work schedule for the project team to follow.