CompTIA Project+ Certification (2025) PK0-005 Question # 17 Topic 2 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 17 Topic 2 Discussion

PK0-005 Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?


A.

Add a new risk.


B.

Perform an impact analysis.


C.

Escalate to the sponsor.


D.

Raise a change request.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.