CompTIA Project+ Certification (2026) PK0-005 Question # 112 Topic 12 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 112 Topic 12 Discussion

PK0-005 Exam Topic 12 Question 112 Discussion:
Question #: 112
Topic #: 12

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?


A.

Meet with the team and highlight the importance of change management.


B.

Roll back the process and submit a change request.


C.

Document the event as a lesson learned.


D.

Remove the team member who bypassed the CCB process.