Question #: 112
Topic #: 12

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project ' s production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?


A.

Finish-to-start


B.

Start-to-start


C.

Finish-to-finish


D.

Start-to-finish