Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2025) PK0-005 Question # 3 Topic 1 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 3 Topic 1 Discussion

PK0-005 Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

A highly scored negative risk causes a risk trigger, but the issue has not started yet. Which of the following is the next step the project team should take?


A.

Execute the contingency plan


B.

Perform a work-around


C.

Escalate to senior management


D.

Assign a risk owner


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.