A software engineer notices that the newest update to the reporting software includes many new features that were not defined in the requirements document. Which of the following steps should the engineer take next?
When scope changes occur, proper change management is critical. The engineer must submit the change for formal approval before moving forward. Skipping approval would violate governance processes and may introduce compliance or contractual risks.