CIPS Strategic Programme Leadership L6M5 Question # 16 Topic 2 Discussion

CIPS Strategic Programme Leadership L6M5 Question # 16 Topic 2 Discussion

L6M5 Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

XYZ is a large construction organization running five different projects. Each project has a specific type of contract and pricing mechanism.

Your task is to match the correct type of contract and pricing mechanism to each project.

Projects and Descriptions

    Project 1

      Description: Construction of an apartment block, where XYZ is responsible for both design and construction. Upon completion, ownership is transferred to the client.

      Pricing Mechanism: Based on past experience of similar projects.

Project 2

    Description: Facilities management for a 6-year period after construction. The budget is constantly adjusted due to industry volatility.

    Pricing Mechanism: Budget changes continuously over time.

Project 3

    Description: XYZ was involved from an early stage, but does not bear the design risk. The budget resets at the start of each new accounting period.

    Pricing Mechanism: The budget is refreshed periodically.

Project 4

    Description: XYZ is responsible for certain parts of the design and build, while another company handles other aspects. XYZ is paid upon milestone completion.

    Pricing Mechanism: Payment is milestone-based.

Project 5

    Description: Construction of a new toll bridge which will be operated by XYZ for the first 6 years post-construction. The pricing includes costs of raw materials, labor, and a profit margin.

    Pricing Mechanism: Costs plus profit.