Question #: 9
Topic #: 1

Cactus Construction is the Principal Contractor on a housing estate project under an NEC contract. Which of the following scenarios would be a mandatory variation?


A.

the project falls behind the plan due to staff shortages


B.

the client changes their opinion on the design


C.

changes to building regulations


D.

raw material prices increase