Question #: 16
Topic #: 2

Managing an organisation through anEntropy eventrequires a different type of leadership capability including creativity. Which of the following is an example of anentropy eventwithin the external environment?


A.

large-scale restructure leading to 100s of redundancies


B.

a force majeure event


C.

an increase in taxes


D.

an important project deadline is missed