Dependencies are the relation between tasks and dictate the order in which tasks are approached. Claudia is running a tender under the Public Contracts Regulations 2015, and there is a 10-day standstill period before she can draft the contract. What type of dependency is this?


A.

mandatory dependency


B.

external dependency


C.

discretionary dependency


D.

internal dependency