Question #: 46
Topic #: 5

The supplier is responsible for delivering the goods to a named port or destination (such as an air-port or warehouse), as well as unloading them from the terminal from this point, risk passes to the buyer.


A.

DAT – Delivered At Terminal


B.

DAP – Delivered At Place


C.

DP – Delivery Duty Paid


D.

FAS – Free Alongside Ship