L4M6 Exam Topic 7 Question 61 Discussion:
Question #: 61
Topic #: 7

Which one of the following is an advantage of early supplier involvement?


A.

Supplier is responsible for all intellectual property risks


B.

Large investment in supplier communications


C.

Understanding of supplier capabilities


D.

No need for supplier non-disclosure agreements