Question #: 3
Topic #: 1

Builder Inc is a rapidly expanding business in construction sector. Due to an increase in projects, it cannot manage the flow of materials by Excel spreadsheets but by more dedicated software. Who would be a key internal stakeholder in defining software compatibility with company's current system?


A.

Procurement team


B.

IT team


C.

Executive team


D.

Finance team