A new product is being manufactured for the first time. The first unit required 600 minutes of labor to manufacture. It is expected that there will be a 90% learning curve for the first 20 units.
The learning index for a 90% learning curve is - 0.152.
Calculate the expected labor time to manufacture the 10th unit.
Your answer should be given to the nearest whole minute.