Which of the following statements are not true about Gantt Charts, Resource Histograms and Work Breakdown Structures?
Select ALL that apply.
Critical activities can be identified using Gantt Charts
A Work Breakdown Structure will help to produce a clear list of individual tasks involved to complete each project element
Statement of Work (SOW) outlines the objectives against which Work Packages must be measured
Work Breakdown Structures cannot be used to determine resource requirements
Gantt Charts clearly identify key activities that must be completed before others begin
Resource Histograms are particularly useful where there are complicated resources to manage
Resource Histograms graphically show the resources required over the term of the project