CIMA Project and Relationship Management E2 Question # 63 Topic 7 Discussion

CIMA Project and Relationship Management E2 Question # 63 Topic 7 Discussion

E2 Exam Topic 7 Question 63 Discussion:
Question #: 63
Topic #: 7

Which of the following statements are not true about Gantt Charts, Resource Histograms and Work Breakdown Structures?

Select ALL that apply.


A.

Critical activities can be identified using Gantt Charts


B.

A Work Breakdown Structure will help to produce a clear list of individual tasks involved to complete each project element


C.

Statement of Work (SOW) outlines the objectives against which Work Packages must be measured


D.

Work Breakdown Structures cannot be used to determine resource requirements


E.

Gantt Charts clearly identify key activities that must be completed before others begin


F.

Resource Histograms are particularly useful where there are complicated resources to manage


G.

Resource Histograms graphically show the resources required over the term of the project


Get Premium E2 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.