CIMA Project and Relationship Management E2 Question # 25 Topic 3 Discussion

CIMA Project and Relationship Management E2 Question # 25 Topic 3 Discussion

E2 Exam Topic 3 Question 25 Discussion:
Question #: 25
Topic #: 3

A small project has been planned based on the following set of activities:

 

Apply critical path analysis and identify the correct statement:

The critical path runs through A,B,D,E and C has 2 days of float (free slack)


A.

The critical path runs through A,B,D,E and C has 6 days of float (free slack)


B.

The critical path runs through A,C,E and B has 5 days of float (free slack)


C.

The critical path runs through A,C,E and D has 4 days of float (free slack)