A small project has been planned based on the following set of activities:
Apply critical path analysis and identify the correct statement:
The critical path runs through A,B,D,E and C has 2 days of float (free slack)
The critical path runs through A,B,D,E and C has 6 days of float (free slack)
The critical path runs through A,C,E and B has 5 days of float (free slack)
The critical path runs through A,C,E and D has 4 days of float (free slack)
<title version="1.0" width="245" border="1" bgcolor="#FFFFFF" >
width="70" />
width="105" />
Activity Duration Predecessor/s
Activity
Duration
Predecessor/s
A
2 days
-
B
5 days
C
6 days
D
3 days
E
1 day
C,D