New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CIMA Project and Relationship Management E2 Question # 23 Topic 3 Discussion

CIMA Project and Relationship Management E2 Question # 23 Topic 3 Discussion

E2 Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

Which of the following is NOT designed to deal with risk and uncertainty when planning for time?


A.

Project evaluation and review


B.

Resource histogram


C.

Buffering


D.

Scenario Planning


Get Premium E2 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.