The Board of organisation Y has authorised an upgrade to its computerised finance system.

 

The Finance Director, X, has been tasked with managing this project.  X has been requested to consult with stakeholders, in order that a Project Initiation Document (PID) may be produced.

 

What are the TWO main uses of a PID?


A.

To ensure that the project is broken down into work packages and a Work Breakdown Structure be produced.


B.

To produce a risk assessment of both internal and external risks that are likely to effect the project, and alternative actions to reduce the risks.


C.

To ensure that the project has a complete sound basis before any major commitment to the project.


D.

To act as a base document against which the project can be managed for progress, change management issues, and ongoing viability issues.