Examine the network diagram shown and identify ALL of the statements below that are true.

E2 Question 5


A.

Task C is a predecessor of E


B.

Task G may begin when either Task B or Task F have finished


C.

When Task A is complete, three tasks may begin


D.

Task D is a successor to F