Users are complaining to you that the Milestones related list is not showing the most useful fields on the Project page. Which sequence of steps would you take to update the fields?
A.
Go to the Project object > Project Page Layout > Milestones Related List > Update fields
B.
Go to the Milestone object > Milestone Page Layout > Project Related List > Update fields
C.
Go to the Milestone object > Fields Sets > Project Field Set > Update fields
To update theMilestones related liston the Project page with the most useful fields:
Go to Setup→ Object Manager.
Find and open the "Project" object.
Navigate to Page Layoutsand select the active layout.
Scroll to the "Milestones" related list.
Modify the fields displayed(e.g., Target Date, Amount, Status, etc.).
Save the changes and refresh the page.
Option B (Updating the Milestone Page Layout instead of Project Page Layout)is incorrect because the Milestone object does not control related lists on the Project page.
Option C (Updating the Project Field Set on the Milestone object)is incorrect because field sets control default field visibility, not related lists.
Thus, the correct answer isA.
References:
PSA Sys Admin Essentials Student Guide Fall 20
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit