BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 85 Topic 9 Discussion

BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 85 Topic 9 Discussion

RCDDv14.1 Exam Topic 9 Question 85 Discussion:
Question #: 85
Topic #: 9

The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff

What should the program manager do to ensure communications on the component projects are consistent?


A.

Request a more experienced project manager to work on project 6


B.

Create a program communications management plan across all component projects


C.

Direct all projects to use project A's communications management plan as a template


D.

Rework the communications management plans for all projects to be consistent


Get Premium RCDDv14.1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.