BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 64 Topic 7 Discussion

BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 64 Topic 7 Discussion

RCDDv14.1 Exam Topic 7 Question 64 Discussion:
Question #: 64
Topic #: 7

A manufacturing company is redesigning various component projects that comprise a large customer-facing program. One of the component projects is payment of back-end rebates. There is disagreement between the marketing and sales teams on how much should be rebated.

What are suggested standard measurement criteria for the success of all constituent projects to meet stakeholder expectations''


A.

Stakeholder engagement plan, risk management plan, and communications management plan


B.

Needs analysis, feasibility study, and integrated benefits management plan


C.

Cost-benefit analysis ROI and payback period


D.

Actual cost (AC), planned value (PV) and earned value (EV)


Get Premium RCDDv14.1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.