BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 52 Topic 6 Discussion

BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 52 Topic 6 Discussion

RCDDv14.1 Exam Topic 6 Question 52 Discussion:
Question #: 52
Topic #: 6

Which two of the following documents MUST be submitted by the communication's project contractor for review and approval? {Select two options.)


A.

Test reports


B.

Shop drawings


C.

Cost summary


D.

Site survey


E.

Request for information (RFI)