BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 42 Topic 5 Discussion

BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 42 Topic 5 Discussion

RCDDv14.1 Exam Topic 5 Question 42 Discussion:
Question #: 42
Topic #: 5

After taking over a program, a program manager reviews the program's status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs The program manager establishes earned value (EV) metrics and determines that the program has a budget of USS2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000

Based on this information, the program manager determines which of the following?


A.

The schedule is US%30.000 under budget


B.

The cost is US$20.0O0 under budget


C.

The schedule is US$10.000 over budget


D.

The cost is USS20.000 over budget


Get Premium RCDDv14.1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.