BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 19 Topic 2 Discussion

BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 19 Topic 2 Discussion

RCDDv14.1 Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

The number of emerging risks increases in a component project and the program manager tails behind in reviewing) and approving the plans. This Impacts the component project manager's ability to effectively address the risks.

In this situation, what should the program manager change about the risk management plan?


A.

Allow the component project manager to delegate risk management responsibilities


B.

Assign the resolution of project-level risks to the component project manager


C.

Include risk escalation policies and procedures in the risk response plan


D.

Increase flexibility with risks that require a risk response


Get Premium RCDDv14.1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.