BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 14 Topic 2 Discussion

BICSI Registered Communications Distribution Designer – RCDDv14.1 RCDDv14.1 Question # 14 Topic 2 Discussion

RCDDv14.1 Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

RCDDv14.1 Question 14

The above performance report shows the earned value (EV) analysis for a program The program director performs a high-level analysis and must present a summary narrative to the steering committee

What do the current findings show?


A.

Project C is running behind schedule and is over budget, projects A, B and D are on schedule


B.

Project A is running ahead of schedule and is under budget projects B, C and D are behind schedule


C.

The overall program is performing within an acceptable level of variance


D.

Project A is running behind schedule and is over budget projects B, C. and D are on schedule


Get Premium RCDDv14.1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.