The above performance report shows the earned value (EV) analysis for a program The program director performs a high-level analysis and must present a summary narrative to the steering committee
What do the current findings show?
A.
Project C is running behind schedule and is over budget, projects A, B and D are on schedule
B.
Project A is running ahead of schedule and is under budget projects B, C and D are behind schedule
C.
The overall program is performing within an acceptable level of variance
D.
Project A is running behind schedule and is over budget projects B, C. and D are on schedule
Chosen Answer: