BICSI Registered Communications Distribution Designer – RCDDv14 RCDDv14 Question # 77 Topic 8 Discussion

BICSI Registered Communications Distribution Designer – RCDDv14 RCDDv14 Question # 77 Topic 8 Discussion

RCDDv14 Exam Topic 8 Question 77 Discussion:
Question #: 77
Topic #: 8

The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B.

This is an example of which of the following?


A.

Program resource management planning


B.

Program risk mitigation


C.

Resource interdependency management


D.

Project resource planning


Get Premium RCDDv14 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.