RCDDv14 Exam Topic 8 Question 75 Discussion:
Question #: 75
Topic #: 8

Company A recently signed a contract with a strategic business partner, Company B, to jointly roll out a new technology Company B is excited about the joint marketing opportunity Company A's component Quality Assurance team has expressed concerns to you the program manager, Ural the product is being rolled out prematurely and has identified potential issues with backend support systems. QA, however, assures you that a manual work around is possible, but not ideal Company B requests an enhancement to the new product. In a meeting with Company B, you determine that additional funding will be required and resources allocated and scheduled

What is your MOST appropriate next step?


A.

Secure funding from another project that was cancelled


B.

Use an integrated change control process


C.

Use the available management reserve


D.

Advise Company B that funding and resources are not available