A program is completed and the expected benefits are realized Before executing the transition and closing of the program, what should the program manager do?
A.
Create a final program report.
B.
Archive documents and lessons learned
C.
Obtain approval from the program governance board to initiate program closure activities
D.
Perform administrative and program management information system (PMIS) closure activities.
Chosen Answer: