A program manager recognizes that a successful resource being used in project A could also be used in project B. What should the program manager do first to leverage the utilization of this resource?
A.
Assign project A's resource to project B
B.
Reassign the resource to project B after protect A ends
C.
Prioritize the resource to optimize their use across both projects A and B
D.
Mitigate risk by leveraging other resources in project A