BICSI Registered Communications Distribution Designer – RCDDv14 RCDDv14 Question # 34 Topic 4 Discussion

BICSI Registered Communications Distribution Designer – RCDDv14 RCDDv14 Question # 34 Topic 4 Discussion

RCDDv14 Exam Topic 4 Question 34 Discussion:
Question #: 34
Topic #: 4

A program manager recognizes that a successful resource being used in project A could also be used in project B. What should the program manager do first to leverage the utilization of this resource?


A.

Assign project A's resource to project B


B.

Reassign the resource to project B after protect A ends


C.

Prioritize the resource to optimize their use across both projects A and B


D.

Mitigate risk by leveraging other resources in project A


Get Premium RCDDv14 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.