Assume you are a test manager of a project that develops software in the medical domain. You are responsible for analysing the organisational test strategy and the project context to choose the appropriate test approach.
You consider the following factors:
Detailed requirements of high quality are available
Parts of the software to be developed are expected to be safety critical
Internal audits and an external audit by a government agency are expected to take place, as such traceability and evidence are important elements for the test approach
A release date has been defined, and a marketing campaign has already been scheduled
The project works according to the sequential V-model lifecycle
The independent test team has a lot of domain knowledge but has also been trained and has experience in using test design techniques
Which of the following test approaches would be most appropriate for this project?