BCS ISTQB Certified Tester Advanced Level - Test Management v3.0 TM3 Question # 2 Topic 1 Discussion

BCS ISTQB Certified Tester Advanced Level - Test Management v3.0 TM3 Question # 2 Topic 1 Discussion

TM3 Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

A project has been running for a few months and the team does not seem to be making progress in their test approach. The team also lacks drive and enthusiasm and is sometimes seen to be performing their tasks too slowly. You have been asked to recruit an extra person into the team. In addition to introducing the new team member, you have decided to raise motivation.

Which of the actions listed below would most likely result in the opposite, a de-motivation of the team?


A.

Criticising testers only in private when they made a mistake during their test activities.


B.

Constantly prescribing overtime to the testers so that they will be accustomed to perform extra hours when necessary.


C.

Providing adequate rewards to the testers when they have done an outstanding job.


D.

Organising a meeting with senior management in which senior management addresses the importance of good testing for this project.