ISEB-PM1 Exam Topic 6 Question 56 Discussion:
Question #: 56
Topic #: 6

Your company has asked you to be the project manager for the product introduction of its new DeskTop Rock media system. You recently published the project scope statement.

Which of the following is not contained in the project scope statement?


A.

Requested changes


B.

Project configuration management requirements


C.

Constraints


D.

Project specifications