BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 49 Topic 5 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 49 Topic 5 Discussion

ISEB-PM1 Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5

How is quality control performed?


A.

By identifying quality standards that are relevant to the project and determining how to satisfy them.


B.

By monitoring specific project results in compliance with relevant quality standards and determining corrective actions as needed.


C.

By ensuring that the entire project team has been adequately trained in quality assurance processes.


D.

By applying Monte Carlo, sampling, Pareto analysis and benchmarking techniques to ensure conformance to quality standards.


Get Premium ISEB-PM1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.