ISEB-PM1 Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measure for a future project?


A.

Bottom-up estimating


B.

Analogous estimating


C.

Parametric estimating


D.

Three-point estimates