BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 41 Topic 5 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 41 Topic 5 Discussion

ISEB-PM1 Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed.

What is the cost variance?


A.

-$700


B.

-$200


C.

+$200


D.

+$500


Get Premium ISEB-PM1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.