BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 41 Topic 5 Discussion
ISEB-PM1 Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5
A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed.