BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 36 Topic 4 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 36 Topic 4 Discussion

ISEB-PM1 Exam Topic 4 Question 36 Discussion:
Question #: 36
Topic #: 4

Which of the following is the LEAST effective way to influence the factors that create changes to the cost baseline?


A.

Review the project scope with the functional manager responsible for the greatest number of requested changes.


B.

Explain to those requesting changes the negative impact of change to the project.


C.

Eliminate the scope causing the most changes.


D.

Notify all stakeholders that no more changes will be allowed.


Get Premium ISEB-PM1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.