BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 34 Topic 4 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 34 Topic 4 Discussion

ISEB-PM1 Exam Topic 4 Question 34 Discussion:
Question #: 34
Topic #: 4

Which of the following would be the MOST appropriate thing to do during the planning process group?


A.

Update corporate processes and procedures based on lessons learned.


B.

Evaluate the effectiveness of risk responses.


C.

Recommend changes and defect repair.


D.

Work with the customer to determine acceptance criteria.