ISEB-PM1 Exam Topic 3 Question 28 Discussion:
Question #: 28
Topic #: 3

Which of the following inputs is required for the WBS creation?


A.

Project Quality Plan


B.

Project Schedule Network


C.

Project Management Software


D.

Project Scope Management Plan