BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 24 Topic 3 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 24 Topic 3 Discussion

ISEB-PM1 Exam Topic 3 Question 24 Discussion:
Question #: 24
Topic #: 3

The project manager has performed schedule network analysis, compressed the schedule, and completed a Monte Carlo analysis.

What time management activity should be done NEXT?


A.

Update resource requirements


B.

Recommend corrective actions


C.

Estimate Activity Durations


D.

Create a milestone list


Get Premium ISEB-PM1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.