BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 15 Topic 2 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 15 Topic 2 Discussion

ISEB-PM1 Exam Topic 2 Question 15 Discussion:
Question #: 15
Topic #: 2

Risk mitigation includes all but which of the following:


A.

performing contingent planning


B.

Obtaining insurance against loss


C.

Developing system (policies, procedures, responsibilities)


D.

identification of project risks.


E.

developing planning alternatives