Based on the chart, while completing the project, a team member tells you that the team forgot something during planning. Activity F needs the results of activity E before it can begin.

Taking this new dependency into account, what would be the effect on the project?


A.

It would increase the critical path.


B.

Communication would be more complex.


C.

There would be no effect.


D.

It would delay activity F.