BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 11 Topic 2 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 11 Topic 2 Discussion

ISEB-PM1 Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

In which type of organization(s) is the project manager's role most likely part-time?


A.

Functional


B.

Weak Matrix


C.

Balanced Matrix


D.

Both 1) Functional and 2) Weak Matrix