ISEB-PM1 Exam Topic 18 Question 178 Discussion:
Question #: 178
Topic #: 18

You are working with XYZ organization. Your senior manager imposed new delivery date which is earlier than mentioned project deliverables date in scope statement.

To whom you are most accountable?


A.

customer


B.

team member


C.

sponsor


D.

senior manager